Draft Annual Electricity Transmission Performance Report 2021 and the Draft Investment Planning and Delivery Report 2021 Consultation - Outcomes

Dúnta8 Sam, 2022, 5:30pm - 7 Nol, 2022, 5:30pm

Primary tabs

The consultation

EirGrid and ESB Networks, as TSO and TAO respectively, published the Draft Annual Electricity Transmission Performance Report 2021 and the Draft Investment Planning and Delivery Report 2021 for consultation seeking customers’ and stakeholders’ feedback on these draft reports in advance of their finalisation.

The CRU, via the PR5 Regulatory Framework, Incentives and Reporting Decision Paper CRU/20/154, requires the TAO and the TSO to produce joint reports setting out their annual performance with regard to the operation and development of the Transmission System. These reports are intended to provide customers, industry participants and other interested parties with a clear, accessible, comprehensive, quantified but non-technical report on performance in the calendar year.

 

Your views and suggestions

With respect to the draft reports published for consultation, we welcomed responses to the following questions:

Q1: Are there areas within the Draft Annual Electricity Transmission Performance Report 2021 that you feel require more detailed information?

Q2: Are there areas within the Draft Investment Planning and Delivery Report 2021 that you feel require more detailed information?

 

Outcomes

Please see below the final documents and consultation response documents that address feedback received in this consultation.

 

Ceisteanna

C1. Are there areas within the Draft Annual Electricity Transmission Performance Report 2021 that you feel require more detailed information?
C2. Are there areas within the Draft Investment Planning and Delivery Report 2021 that you feel require more detailed information?