Option F North Wall to Poolbeg

Closed28 Mar, 2023, 1:00pm - 23 May, 2023, 5:00pm

Option F : North Wall to Poolbeg

Option F leaves the North Wall substation heading east on Alexandra Road. At Breakwater Road, the route turns south onto Breakwater Road towards the River Liffey. At the end of Breakwater Road, the route crosses the Lower Liffey Estuary onto Dublin Port Company Lands (DPC) on the southern bank. The crossing methodology will most likely be Horizontal Directional Drilling (HDD) and site investigations will determine the preferred crossing route.
On the southern bank, the route crosses the DPC land to Pigeon House Road, which it follows east as far as the Poolbeg substation.

Map of Option F

Click to zoom and enlarge